Having announced a target of £44,000 to complete the bottom part of its new steam locomotive, so that it can be demonstrated working by means of compressed air in September 2020 during the Open Day at Alan Keef Ltd, the Corris Railway is pleased that funds are now in place to complete the outside motion.
Looking at other areas of the project it is estimated that a sum in excess of £30,000 from the final overall bill will be saved by reason of Corris Railway volunteers constructing some parts of No.
The visit to Keef’s also saw the pony truck complete with trailing wheels delivered to the works following construction and assembly by Corris volunteers.