Track removal began in earnest late on Tuesday with 8 lengths being removed.
Wednesday (the wet day of the week) saw 25 lengths of track taken out, with the last panels removed on Thursday.
Relaying of the track started on Friday with trial lengths laid to test plant and equipment.