Tracklaying has resumed again; those who visited our September open days will have seen trains operating on what is known as the Red Shed Bypass line; the main passenger running line will run parallel to the Bypass line, then alongside the large Aurora North storage shed, and then beside the site access road until the Stage One terminus at Apedale Road is reached.
Whilst this churns through the corridors of power, we have commenced work on the railway alongside the access road.
Thus far, two approaches have been tried – firstly to build the track into panels elsewhere on site, and then transport by crane to site and lay into position.