News Archive

Wharf Redevelopment - Progress report

Published and found at

The brick perimeter wall alongside Neptune Road has been built and the pedestrian walk down started – steps are in place but they have to be topped off with paviers.

A layer of bitumastic paint, followed by concrete screed then artificial membrane has been added to the flat standings that lie to the north of the building (between the building and the Neptune Road wall) – all to ensure that water does not fall through into the kitchen or the ground floor of the museum; this is to be finished off with paviers in the coming week.

The wing wall of Neptune road bridge is being brought up to pavement level behind the north wall of the Guard’s room using old/second-hand bricks.

Read the full article